UPDATE OF CONSTRUCTION ON NW 6th AVENUE

Updates will be continuously added as this project progresses.

The Pompano Beach Community Redevelopment Agency would like to inform you of planned roadway improvements on NW 6th Avenue

Timeline: Construction is anticipated to be completed in mid-February.

• Access to residences and businesses will be maintained at all times.

The Roadway Improvements include:

Updated 1/29/2026

Removal of existing roundabouts and replacement with raised intersections and controlled stop signs at the following intersections:

NW 6th Avenue and NW 6th Street - COMPLETE

NW 6th Avenue and NW 8th Street - COMPLETE

NW 6th Avenue and NW 10th Street - COMPLETE

Roadway repaving from Atlantic Boulevard to MLK Boulevard will be completed by February 13th. Please see the image below:

Map of construction

For Questions Contact:

Aisha Paul – Community Liaison
(352) 219-0111
info@dudlyservices.com

Evan Camejo – CRA Redevelopment Project Coordinator
(954) 786-5535

Kimberly Vazquez – Redevelopment Project Manager III

(954) 786-4655

Project Map – yellow circled areas show the intersections to be turned into raised intersections with stop signs.